04 · Roadmap

The launch roadmap to 1 December.

Launch about two weeks out, once the ad scripts, the VSL and everything are in. The gate is assets, not the date: if the VSL, the ad scripts and Danny's recordings are not approved by 25 November, launch moves a week. Dates are targets.

00 · The date

Launch target.

Tue 1 Dec

Assets approved by 25 November, or the launch moves a week.

PhaseDatesWhat
0. Strategy lockedDone, 5 NovICP, method, ladder, delivery, entry product, application, sales SOP and deck
1. Danny signs off6 to 11 NovSeason 2 form, one price on calls, the gameplan presented
2. Assets written9 to 18 NovVSL, ad scripts, page copy, recording list, templates, protocols
3. Shoot and build16 to 25 NovRecording days, edits, application, Starter Plan app, CRM, CSM in place
4. Test and train23 to 30 NovSales training, end-to-end test, campaign build, reactivation
5. Launch1 DecF1 and F2 live in India; diaspora tests live
6. Run and measureDecember onFirst cohort, scorecards, the next Refinery
01 · Phases

Phases, tasks, owners, dates.

0Done, 5 November

Strategy locked

ICP v3 (senior professionals core, experiments separate), Made to Measure (Measure, Reset, Build, Finish), the Refinery alongside, continuity (the circle), delivery playbook, entry product (AI Starter Plan), application spec, sales SOP and deck outline. Prices: 3 months ₹75,000, 6 months ₹1,20,000.

Still to agree: instalment structure, prices abroad, continuity prices, Refinery price and member rate, Starter Plan price inside ₹499 to ₹2,999.

16 to 11 November

Danny signs off

#TaskOwnerBy
1.1Season 2 form back from DannyDanny, Aaron7 Nov
1.2Sales team stops unverified claims and quotes one price (brief from Varun)Varun, closers, setters7 Nov
1.3Present the gameplan (this site) to Danny; agree the Decisions for DannyMohit, Danny10 Nov
1.4Danny confirms his story lines, the real client count, the coach capDanny, Drith (count)11 Nov
1.5Overdue instalment sweep starts (₹6.74L across 21 instalments)Drith, CSM11 Nov
29 to 18 November

Assets written

#TaskOwnerBy
2.1Voice pack v2 approved; VSL script (one belief line, the one-layer fix, Made to Measure)DecentraLabs writes, Mohit approves14 Nov
2.2Ad scripts: core segments C1 to C5, plus small tests for the experimentsDecentraLabs writes, Mohit approves16 Nov
2.3Page copy: application, result screens, Starter Plan page, pre-call video scriptDecentraLabs writes, Mohit approves16 Nov
2.4Recording list for Danny: VSL, ads, the 22 library videos, the welcomeDecentraLabs, Aaron schedules14 Nov
2.5Starter Plan templates (training and diet) approved by Coach RayyanRayyan18 Nov
2.6Build protocols (travel, dinners, festival, shifts, proportion, plateau) and the Look Report template draftedDecentraLabs drafts, Rayyan and the style lead correct18 Nov
2.7Sales deck built; sales SOP approvedDecentraLabs, Mohit13 Nov
316 to 25 November

Shoot and build

#TaskOwnerBy
3.1Recording days: VSL, ad creatives, libraryDanny, editor20 Nov
3.2Edits delivered and approvedEditor, Mohit25 Nov
3.3Application on the new spec, tier routing, embedded calendar, CRM fieldsDecentraLabs, Tousif22 Nov
3.4AI Starter Plan app, Razorpay paywall, webhook to Ultimate OS and Meta CAPIDecentraLabs, Tousif24 Nov
3.5EverFit and Ultimate OS set up for the playbook fields (phase, term, check-ins, proof, consent, instalments)Tousif, Rayyan24 Nov
3.6Intake: health-data and photo consent addedDecentraLabs22 Nov
3.7Tailor partner and blood-review arrangement agreed in writingDanny, Aaron20 Nov
3.8CSM in place (hired or assigned)Danny, Aaron20 Nov
423 to 30 November

Test and train

#TaskOwnerBy
4.1Sales training on the SOP; three mock calls per closer; setter 5-minute drillVarun27 Nov
4.2End-to-end test: application each tier, booking, Starter Plan purchase, CRM, Meta eventsDecentraLabs27 Nov
4.3Campaign build: F1 direct application (India), F2 Starter Plan (India), diaspora test ad sets; multi-advertiser opt-out on every creativeDecentraLabs28 Nov
4.4Reactivation (F6): past buyers and the 28 lapsed clients get continuity, the Refinery or a new termCSM, settersStarts 26 Nov
4.5Danny posts for the core ICP (work, meetings, presence, a founder's day) from the content briefDannyFrom 23 Nov
51 December

Launch

  • F1 direct application and F2 Starter Plan live in India.
  • Diaspora test ad sets live side by side (Gulf, UK, Singapore, Malaysia, Canada, Australia, US).
  • Daily ads report and booking alerts on Discord as today; weekly report on Sundays.
6December on

Run and measure

WhenWhatOwner
Week of 7 DecFirst cohort onboarded on the playbook; Reset under wayRayyan, CSM, style lead
Mid DecemberWebinar, if Danny commits the 2 to 3 hoursDanny
WeeklySales scorecard, delivery scorecard, ad reportVarun, CSM, DecentraLabs
End of DecemberNext Refinery date and price announced to the first cohort and alumniDanny, Mohit
Early JanuaryWeek-4 review of every playbook starting numberMohit, Rayyan
Late JanuaryTier re-measure (30 buyers or 8 weeks)DecentraLabs
02 · Risk

What moves the launch.

  1. The assets are late.

    The VSL, the ad scripts and the recordings are not approved by 25 November.

  2. No CSM by 20 November.

    Nothing in the playbook is enforced without one.

  3. The test fails.

    The application or the Starter Plan checkout fails the end-to-end test.